.png)
Stage two will include construction of the east side of the new concourse, installation of new connectors between concourses C and D, and renovation of Concourse B. A rental car transaction building, a consolidated rental car quick turn-around (QTA) facility, a new central utility plant (CUP) and new roadways will be also constructed. Stage one will include construction of the new terminal and the west side of the new concourse, and renovation of Concourse A. Construction plan for Salt Lake City airport The new terminal, to be built at an estimated cost of $1.8bn, will provide better customer service and accommodate more passengers. The airport terminals and the concourses building, which have been operating for the past 27 to 50 years, have become outdated calling for a major redevelopment. The terminal redevelopment project is being implemented to minimise seismic risks at the airport.